Concentrating Solar Power (CSP)
Concentrating Solar Power (CSP) slipped from an all-time high in production of 885 GWh in 2008 to 862 GWh in 2009. New capacity becoming operational in 2010 pushed production to 1121 GWh and an estimated 1475 GWh in 2011. The wholesale value from this technology, also known as Solar Thermal power, generated $68 USD million in 2008, $102 million in 2009, to $362 million in 2010. 2011 sales should top a half billion dollars at an estimated $545 million.
The cost of the installed base of CSP at the end of 2011 is estimated at $9.5 billion. Of that roughly 93% of the installed base value is in parabolic trough technology. By 2015, that percentage is forecast to drop to 70% as power tower, also called central receiving station technology, becomes more common. The other two CSP technologies, linear Fresnel reflector and the Stirling engine/dish design are decidedly lacking although there are a few small projects going forward.
The seemingly smooth upward curve of CSP productions hides some facts that will impinge future growth. At least 2,250 MW of planned CSP capacity was suddenly switched to PV due to the lower installation costs of PV, among other reasons. Also hidden by the high Spanish feed-in tariff is the somewhat low capacity of the plants in Spain due to less than ideal solar resources. Due to the global debt crisis, Spain had considered cutting its artificially high feed-in tariff, but to preserve investor confidence, has chosen to delay bringing some plants online and limiting the output of others.
Thermal energy storage (TES) became a big topic in 2011 with demonstrations of 24 hour generation at a plant in Spain less than four months after startup. Seven to eight hours’ storage appears to be the norm for parabolic trough plants at a cost of roughly an additional 10-11 % of the plant cost but can yield capacity factors over 50%, a key to profitability. Power towers operating at higher temperatures can achieve 10- 15 hours storage at a slightly less cost penalty.
New development and construction activities will intensify in 2012 in Australia, India, and China. China has licensed technology from eSolar and plans to build 2 GW of combined CSP/biomass plants in the next decade. India too has created a 20 GW by 2020 solar wish list. Australia continues to study the technology and is building a world study center of power tower technology.
As 2011 ends, the global capacity of utility-scale CSP will be right at 2 GW with approximately another 2500 to 3500 MW to be operational in 2012, depending on several factors. While some forecasters believe the US concentrating solar power capacity alone will reach 6 GW by 2015, SBI Energy analysis points to factors that suggest an installation rate that while consistent with the opportunities CSP represents, is more indicative of the current global economic and political realities. These factors include the events known as the Islamic Spring, the overall lingering economic doldrums, and current photovoltaic pricing wars as well as utility concerns regarding implementation of renewables on a large scale. While these concerns are not permanent, they will retard implementation of CSP for a few years.
CSP Energy tends to be CSP installation has been directly linked to government interest in the technology. CSP Global Markets provides insight into the current and future utility scale electrical generation CSP markets at both the plant and component level, with particular attention to the solar field elements which represent over 50% of the plant's cost. For every major component, global market size is provided and forecast through 2020 based on the SBI Energy's evaluation of the factors affecting the market growth as a whole.
The cost of the installed base of CSP at the end of 2011 is estimated at $9.5 billion. Of that roughly 93% of the installed base value is in parabolic trough technology. By 2015, that percentage is forecast to drop to 70% as power tower, also called central receiving station technology, becomes more common. The other two CSP technologies, linear Fresnel reflector and the Stirling engine/dish design are decidedly lacking although there are a few small projects going forward.
The seemingly smooth upward curve of CSP productions hides some facts that will impinge future growth. At least 2,250 MW of planned CSP capacity was suddenly switched to PV due to the lower installation costs of PV, among other reasons. Also hidden by the high Spanish feed-in tariff is the somewhat low capacity of the plants in Spain due to less than ideal solar resources. Due to the global debt crisis, Spain had considered cutting its artificially high feed-in tariff, but to preserve investor confidence, has chosen to delay bringing some plants online and limiting the output of others.
Thermal energy storage (TES) became a big topic in 2011 with demonstrations of 24 hour generation at a plant in Spain less than four months after startup. Seven to eight hours’ storage appears to be the norm for parabolic trough plants at a cost of roughly an additional 10-11 % of the plant cost but can yield capacity factors over 50%, a key to profitability. Power towers operating at higher temperatures can achieve 10- 15 hours storage at a slightly less cost penalty.
New development and construction activities will intensify in 2012 in Australia, India, and China. China has licensed technology from eSolar and plans to build 2 GW of combined CSP/biomass plants in the next decade. India too has created a 20 GW by 2020 solar wish list. Australia continues to study the technology and is building a world study center of power tower technology.
As 2011 ends, the global capacity of utility-scale CSP will be right at 2 GW with approximately another 2500 to 3500 MW to be operational in 2012, depending on several factors. While some forecasters believe the US concentrating solar power capacity alone will reach 6 GW by 2015, SBI Energy analysis points to factors that suggest an installation rate that while consistent with the opportunities CSP represents, is more indicative of the current global economic and political realities. These factors include the events known as the Islamic Spring, the overall lingering economic doldrums, and current photovoltaic pricing wars as well as utility concerns regarding implementation of renewables on a large scale. While these concerns are not permanent, they will retard implementation of CSP for a few years.
CSP Energy tends to be CSP installation has been directly linked to government interest in the technology. CSP Global Markets provides insight into the current and future utility scale electrical generation CSP markets at both the plant and component level, with particular attention to the solar field elements which represent over 50% of the plant's cost. For every major component, global market size is provided and forecast through 2020 based on the SBI Energy's evaluation of the factors affecting the market growth as a whole.
- CHAPTER 1 EXECUTIVE SUMMARY
- CHAPTER 2 BACKGROUND TO CSP MARKETS
- Scope and Methodology of Report
- Market Definition and History
- General CSP Process Description for electricity generation
- Figure 2-1 CSP process schematic
- Market Categories
- Parabolic troughs
- Figure 2-2 Parabolic trough design
- Figure 2-3 Parabolic trough mirror/receiver detail
- Power Towers
- Figure 2-4 Power tower design
- Figure 2-5 Power tower mirror/receiver detail
- Dish/Engine Systems
- Figure 2-6 Dish/Engine design
- Figure 2-7 Dish/engine concentration system detail
- Linear Fresnel Reflectors
- Figure 2-8 Fresnel lens optics
- Figure 2-9 Linear Fresnel reflector detail
- Thermal Storage
- Figure 2-10 Thermal storage schematic detail
- Hybrid Plants
- Figure 2-11 Hybrid Plant Schematic
- Figure 2-12 Hybrid plant power source by hour of the day
- Concentrating Solar for Heat Generation
- Industrial uses of solar heat
- Figure 2-13 CSP -Solar Heat schematic
- Figure 2-14 CSP -Global Industrial use
- Residential uses of solar heat
- Figure 2-15 CSP -US Residential installations
- Comparison of Market Categories
- Table 2-1 Features of CSP Categories
- Table 2-2 Power Generation efficiency by CSP category
- CSP Market Factors
- Climatic Factors
- Table 2-3 Climatic factors vs. Solar Energy Process
- Figure 2-16 Geographic distribution of climatic factors
- Power Distribution Factors
- Table 2-4 Comparison of HVAC vs. HVDC
- Table 2-5 Power generation factors vs. distance to market
- Figure 2-17 Contribution to power grid by CSP category
- Cooling Process Factors
- Table 2-6 Cooling Options
- Figure 2-18 Water cooling schematic
- Figure 2-19 Dry cooling schematic
- The Renewable Power Industry
- Value of Electricity from Renewable Sources
- Public policies affect on Renewable Power Generation
- Policies to Promote Renewable Energy Sources
- Production Tax Credits
- Renewable Portfolio Standards
- Renewable Power Direct Marketing
- Renewable Feed-in-Tariff
- Fossil Fuel Emissions Caps
- Table 2-7 Pros and Cons of public policy use to promote renewable energy generation
- Table 2-8 International public policies
- Research investments in Renewable Energy
- Table 2-9 US government investment in Renewable Energy through 2010
- Table 2-10 Global public investment in Renewable Energy through 2010
- Research Efforts in Solar Power
- Table 2-11 US government investment in Solar Power through 2010
- Table 2-12 US government investment in Solar Power currently allocated
- Table 2-13 Global public investment in Solar Power through 2010
- Table 2-14 Global public investment in Solar Power currently allocated
- Figure 2-20 Public Investments vs. Solar power delivered though 2010
- Figure 2-21 Public Investments vs. Solar power projected 2011- 2020
- Research Efforts in CSP
- Table 2-15 US government investment in CSP Technologies through 2010
- Table 2-16 US government investment in CSP Technologies currently allocated
- Table 2-17 Global public investment in CSP Technologies through 2010
- Table 2-18 Global public investment in CSP Technologies currently allocated
- Figure 2-22 Public Investments vs. CSP power delivered though 2010
- Figure 2-23 Public Investments vs. CSP power projected 2011- 2020
- Renewable Energy Market Size and Growth
- Basis of Forecasts
- PV
- Figure 2-24 US PV Market 2007 - 2011, Nameplate MW Installed
- Figure 2-25 US PV Market 2007 - 2011, Power Output, MW
- Figure 2-26 US ROI on PV Investments 2007 - 2011
- Figure 2-27 US PV Market 2012 - 2016, Nameplate MW Planned
- Figure 2-28 Global PV Market 2007 - 2011, Nameplate MW Installed
- Figure 2-29 Global PV Market 2007 - 2011, Power Output, MW
- Figure 2-30 Global PV Market 2012-2016, Nameplate MW Planned
- Geothermal power
- Figure 2-31 US Geothermal power Market 2007 - 2011, Nameplate MW Installed
- Figure 2-32 US Geothermal power Market 2007 - 2011, Power Output, MW
- Figure 2-33 US ROI on Geothermal power Investments 2007 - 2011
- Figure 2-34 US Geothermal power Market 2012 - 2016, Nameplate MW Planned
- Figure 2-35 Global Geothermal power Market 2007 - 2011, Nameplate MW Installed
- Figure 2-36 Global Geothermal power Market 2007 - 2011, Power Output, MW
- Figure 2-37 Global Geothermal power Market 2012 - 2016, Nameplate MW Planned
- Biopower
- Figure 2-38 US Biopower Market 2007 - 2011, Nameplate MW Installed
- Figure 2-39 US Biopower Market 2007 - 2011, Power Output, MW
- Figure 2-40 US ROI on Biopower Investments 2007 - 2011
- Figure 2-41 US Biopower Market 2012 - 2016, Nameplate MW Planned
- Figure 2-42 Global Biopower Market 2007 - 2011, Nameplate MW Installed
- Figure 2-43 Global Biopower Market 2007 - 2011, Power Output, MW
- Figure 2-44 Global Biopower Market 2012, 2016, Nameplate MW Planned
- Photovoltaics
- Figure 2-45 US PV Market 2007 - 2011, Nameplate MW Installed
- Figure 2-46 US PV Market 2007 - 2011, Power Output, MW
- Figure 2-47 US ROI on PV Investments 2007 - 2011
- Figure 2-48 US PV Market 2012 - 2016, Nameplate MW Planned
- Figure 2-49 Global PV Market 2007 - 2011, Nameplate MW Installed
- Figure 2-50 Global PV Market 2007 - 2011, Power Output, MW
- Figure 2-51 Global PV Market 2012 - 2016, Nameplate MW Planned
- Concentrating Solar Power
- Figure 2-52 US CSP Market 2007 - 2011, Nameplate MW Installed
- Figure 2-53 US CSP Market 2007 - 2011, Power Output
- Figure 2-54 US CSP Market 2007 - 2011, Cost per Unit Installed
- Figure 2-55 US CSP Market 2012, 2016, Nameplate MW Planned
- Figure 2-56 US CSP Market 2012, 2016, Cost per Unit Planned
- Figure 2-57 Global CSP Market 2007 - 2011, Nameplate MW Installed
- Figure 2-58 Global CSP Market 2007 - 2011, Power Output, MW
- Figure 2-59 Global CSP Market 2007 - 2011, Cost per Unit Installed
- Figure 2-60 Global CSP Market 2012 - 2016, Nameplate MW Planned
- Figure 2-61 Global CSP Market 2012, 2016, Cost per Unit Planned
- Concentrating Solar Process Heat
- Figure 2-62 US CSP Market 2007 - 2011, Installations and Capacity
- Figure 2-63 US CSP Market 2007 - 2011, Power Savings
- Figure 2-64 US CSP Market 2007 - 2011, Cost per Unit Installed
- Figure 2-65 US CSP Market 2012, 2016, Nameplate MW Planned
- Figure 2-66 US CSP Market 2012, 2016, Cost per Unit Planned
- Figure 2-67 Global CSP Market 2007 - 2011, Planned installations and capacity
- Figure 2-68 Global CSP Market 2007 - 2011, Planned Power Savings
- Figure 2-69 Global CSP Market 2007 - 2011, Cost per Unit Installed
- Figure 2-70 Global CSP Market 2012 - 2016, Nameplate MW Planned
- Figure 2-71 Global CSP Market 2012, 2016, Cost per Unit Planned
- CHAPTER 3 REGIONAL AND NATIONAL MARKETS
- CSP Global Market Initiative (CSP- GMI)
- Table 3-1 Goals of the CSP-GMI
- Figure 3-1 CSP-GMI Regions
- Middle East --North Africa (MENA)
- MENA Regional issues
- Desertec Industrial Initiative
- Dii GmbH
- Table 3-2 Desertec Supporting Organizations
- Figure 3-2 Desertec claims regarding CSP potential
- Figure 3-3 Desertec vision of MENA power generation and distribution
- Figure 3-4 MENA Regions suitable for CSP vs. implementation issues
- Figure 3-5 MENA Regions suitable for CSP vs. market demand
- Southwest United States-Mexico (USMEX)
- USMEX Regional issues
- Figure 3-6 USMEX Regions suitable for CSP vs. implementation issues
- USMEX Regional markets
- Figure 3-7 USMEX Regions suitable for CSP vs. market demand
- Southern Europe (SoEur)
- SoEur Regional issues
- Figure 3-8 SoEur Regions suitable for CSP vs. implementation issues
- SoEur Regional markets
- Figure 3-9 SoEur Regions suitable for CSP vs. market demand
- National Markets
- Algeria
- Algerian development activities to date
- Table 3-3 Algerian development efforts through 2011
- Algerian installed and planned capacities
- Table 3-4 Algerian installed and planned capacities through 2011
- Algerian-specific issues
- Algerian CSP market forecast 2012 - 2016
- Figure 3-10 Algerian CSP market forecast 2012 - 2016
- Australia
- Australian development activities to date
- Table 3-5 Australian development efforts through 2011
- Australian installed and planned capacities
- Table 3-6 Australian installed and planned capacities through 2011
- Australian-specific issues
- Australian CSP market forecast 2012 - 2016
- Figure 3-11 Australian CSP market forecast 2012 - 2016
- Brazil
- Brazilian development activities to date
- Table 3-7 Brazilian development efforts through 2011
- Brazilian installed and planned capacities
- Table 3-8 Brazilian installed and planned capacities through 2011
- Brazilian-specific issues
- Brazilian CSP market forecast 2012 - 2016
- Figure 3-12 Brazilian CSP market forecast 2012 - 2016
- Figure 3-13 Chilean CSP market forecast 2012 - 2016
- China
- Chinese development activities to date
- Table 3-9 Chinese development efforts through 2011
- Chinese installed and planned capacities
- Table 3-10 Chinese installed and planned capacities through 2011
- Chinese-specific issues
- Chinese CSP market forecast 2012 - 2016
- Figure 3-14 Chinese CSP market forecast 2012 - 2016
- Egypt
- Egyptian development activities to date
- Table 3-11 Egyptian development efforts through 2011
- Egyptian installed and planned capacities
- Table 3-12 Egyptian installed and planned capacities through 2011
- Egyptian-specific issues
- Egyptian CSP market forecast 2012 - 2016
- Figure 3-15 Egyptian CSP market forecast 2012 - 2016
- Greece
- Grecian development activities to date
- Table 3-13 Grecian development efforts through 2011
- Grecian installed and planned capacities
- Table 3-14 Grecian installed and planned capacities through 2011
- Grecian-specific issues
- Grecian CSP market forecast 2012 - 2016
- Figure 3-16 Grecian CSP market forecast 2012 - 2016
- India
- Indian development activities to date
- Table 3-15 Indian development efforts through 2011
- Indian installed and planned capacities
- Table 3-16 Indian installed and planned capacities through 2011
- Indian-specific issues
- Indian CSP market forecast 2012 - 2016
- Figure 3-17 Indian CSP market forecast 2012 - 2016
- Iran
- Iranian development activities to date
- Table 3-17 Iranian development efforts through 2011
- Iranian installed and planned capacities
- Table 3-18 Iranian installed and planned capacities through 2011
- Iranian-specific issues
- Iranian CSP market forecast 2012 - 2016
- Figure 3-18 Iranian CSP market forecast 2012 - 2016
- Israel
- Israeli development activities to date
- Table 3-19 Israeli development efforts through 2011
- Israeli installed and planned capacities
- Table 3-20 Israeli installed and planned capacities through 2011
- Israeli-specific issues
- Israeli CSP market forecast 2012 - 2016
- Figure 3-19 Israeli CSP market forecast 2012 - 2016
- Italy
- Italian development activities to date
- Table 3-21 Italian development efforts through 2011
- Italian installed and planned capacities
- Table 3-22 Italian installed and planned capacities through 2011
- Italian-specific issues
- Italian CSP market forecast 2012 - 2016
- Figure 3-20 Italian CSP market forecast 2012 - 2016
- Jordan
- Jordanian development activities to date
- Table 3-23 Jordanian development efforts through 2011
- Jordanian installed and planned capacities
- Table 3-24 Jordanian installed and planned capacities through 2011
- Jordanian-specific issues
- Jordanian CSP market forecast 2012 - 2016
- Figure 3-21 Jordanian CSP market forecast 2012 - 2016
- Mexico
- Mexican development activities to date
- Table 3-25 Mexican development efforts through 2011
- Mexican installed and planned capacities
- Table 3-26 Mexican installed and planned capacities through 2011
- Mexican-specific issues
- Mexican CSP market forecast 2012 - 2016
- Figure 3-22 Mexican CSP market forecast 2012 - 2016
- Morocco
- Moroccan development activities to date
- Table 3-27 Moroccan development efforts through 2011
- Moroccan installed and planned capacities
- Table 3-28 Moroccan installed and planned capacities through 2011
- Moroccan-specific issues
- Moroccan CSP market forecast 2012 - 2016
- Figure 3-23 Moroccan CSP market forecast 2012 - 2016
- South Africa
- South African development activities to date
- Table 3-29 South African development efforts through 2011
- South African installed and planned capacities
- Table 3-30 South African installed and planned capacities through 2011
- South African-specific issues
- South African CSP market forecast 2012 - 2016
- Figure 3-24 South African CSP market forecast 2012 - 2016
- Spain
- Spanish development activities to date
- Table 3-31 Spanish development efforts through 2011
- Spanish installed and planned capacities
- Table 3-32 Spanish installed and planned capacities through 2011
- Spanish-specific issues
- Spanish CSP market forecast 2012 - 2016
- Figure 3-25 Spanish CSP market forecast 2012 - 2016
- United States
- US development activities to date
- Table 3-33 US development efforts through 2011
- US installed and planned capacities
- Table 3-34 US installed and planned capacities through 2011
- US-specific issues
- US CSP market forecast 2012 - 2016
- Figure 3-26 US CSP market forecast 2012 - 2016
- African Nation’s Activities
- Other African national development activities to date
- Table 3-35 Other African national development efforts through 2011
- Other African nation’s installed and planned capacities
- Table 3-36 Other African nation’s installed and planned capacities through 2011
- Other-African national specific issues
- Other National Activities
- Other national development activities to date
- Table 3-37 Other national development efforts through 2011
- Other nation’s installed and planned capacities
- Table 3-38 Other nation’s installed and planned capacities through 2011
- Other national specific issues
- CHAPTER 4 CSP COMPONENTS: DESCRIPTION, USE, AND MARKETS
- Basis of Forecasts
- Figure 4-1 Components as a percentage of plant costs
- Engineering, Construction, and Procurement Companies
- Table 4-1 ECP firms for installed and planned CSP facilities
- Figure 4-2 Market share by EPC firm
- High Tech Components
- Mirrors, Frames and Cleaning Systems
- Desired properties of CSP mirrors
- Mirrors: Glass, plastic film. or polished metal
- Table 4-2 Feature comparison between mirror materials
- Research in material choice
- Table 4-3 Global research in mirror materials
- Table 4-4 Research in CSP mirrors
- Installed and planned installations of mirrors
- Table 4-5 Installed mirrors by material options
- Table 4-6 Planned installations of mirrors by material options
- Mirrors Producers
- Table 4-7 Global mirror manufacturers, installed and planned
- Mirror Market and Forecasts
- Figure 4-3 US and Global CSP Mirror Market: 2007 - 2011
- Figure 4-4 US and Global CSP Mirror Market: 2012 - 2016
- Figure 4-5 US and Global CSP Mirror Market: 2016 - 2020
- Frame systems
- Table 4-8 Global CSP Frames manufacturers, installed and planned
- Figure 4-6 US and Global CSP Frames Market: 2007 - 2011
- Figure 4-7 US and Global CSP Frames Market: 2012 - 2016
- Cleaning Systems
- Table 4-9 Cleaning system manufacturers, installed and planned
- Figure 4-8 US and Global CSP Cleaning System Market: 2007 - 2011
- Figure 4-9 US and Global CSP Cleaning System Market: 2012 - 2016
- Receivers and Heat Flow Systems
- Receiver, receiver support and interconnections
- Desirable properties in receivers
- Table 4-10 Feature comparison between Receiver designs
- Research in Receiver Design
- Table 4-11 Research in receiver design and materials
- Installed and planned installations of mirrors
- Table 4-12 Installed receivers by design
- Table 4-13 Planned installations of receivers by design
- Current Receiver Producers
- Table 4-14 Manufacturers of receiver components
- Receiver Market and Forecasts
- Figure 4-10 US and Global CSP Receiver Market: 2007 - 2011
- Figure 4-11 US and Global CSP Receiver Market: 2012 - 2016
- Collection, piping, valves and traps
- Issues unique to CSP
- Operating temperature range
- Environmental conditions
- Length of service
- Longevity of service
- Accessibility for preventative maintenance and performance issues
- Table 4-15 Collection and piping issues unique to CSP
- Companies with installed piping systems and experience
- Table 4-16 Companies with installed piping systems and experience
- Collection as a function of plant parameters
- Heat Transfer Fluid (HTF)
- Desirable properties in HTF
- Table 4-17 Feature comparison between HTF systems
- Research in heat transfer fluids
- Table 4-18 Research in heat transfer fluids
- Installed and planned installations of HTF
- Table 4-19 Heat transfer fluids in installed CSP plants
- Table 4-20 Heat transfer fluids selected for planned CSP plants
- HTF Market and Forecast
- Figure 4-12 US and Global CSP HTF Market: 2007 - 2011
- Figure 4-13 US and Global CSP HTF Market: 2012 - 2016
- Established Components
- Steam Generation Plant
- Table 4-21 Unique CSP Steam Plant Requirements/ Opportunities
- Figure 4-14 US and Global CSP Steam Plant Installations
- Figure 4-15 US and Global CSP Steam Plant Market Forecast 2012 - 2017
- Cooling
- Table 4-22 Unique CSP Cooling Requirements/ Opportunities
- Figure 4-16 US and Global CSP Cooling Installations
- Figure 4-17 US and Global CSP Cooling Market Forecast 2012 - 2017
- Thermal Storage by Molten Salts
- Table 4-23 Unique CSP Thermal Storage Requirements/ Opportunities
- Figure 4-18 US and Global CSP Thermal Storage Installations
- Figure 4-19 US and Global CSP Thermal Storage Market Forecast 2012 - 2017
- Sun Tracking Systems
- Table 4-24 Unique CSP Sun Tracking Requirements/ Opportunities
- Figure 4-20 US and Global CSP Sun Tracking Installations
- Figure 4-21 US and Global CSP Sun Tracking Market Forecast 2012 - 2017
- Materials of Construction
- Figure 4-22 Percentage of cost of CSP installations by material of construction
- Significant issues concerning materials of construction: availability, cost
- Steel
- Table 4-25 Steel usage in CSP
- Figure 4-23 US and Global steel market forecast in CSP, 2012 -2016
- Copper
- Table 4-26 Copper usage in CSP
- Figure 4-24 US and Global copper market forecast in CSP, 2012 -2016
- Brass
- Table 4-27 Brass usage in CSP
- Figure 4-25 US and Global brass market forecast in CSP, 2012 -2016
- Aluminum
- Table 4-28 Aluminum usage in CSP
- Figure 4-26 US and Global aluminum market forecast in CSP, 2012 -2016
- Concrete
- Table 4-29 Concrete usage in CSP
- Figure 4-27 US and Global concrete market forecast in CSP, 2012 -2016
- Molten Salts
- Table 4-30 Molten salts usage in CSP
- Figure 4-28 US and Global molten salts market forecast in CSP, 2012 -2016
- Silica
- Table 4-31 Silica usage in CSP
- Figure 4-29 US and Global silica market forecast in CSP, 2012 -2016
- CHAPTER 5 MARKET PROMOTION, DISTRIBUTION, AND TRENDS
- Promotion of CSP Market
- General environmental movement
- Figure 5-1 Growth in public demand for renewable energy sourcing
- Desire for energy independence
- Table 5-1 History of energy independence efforts in the US
- Fear of lack of access to oil
- Table 5-2 Relationship between the “Islamic Spring” uprisings, oil resources, and CSP investments
- Fear of nuclear power
- Table 5-3 Shifts in perception of nuclear power after 2010 Japanese tsunami
- Electrical Distribution by Region
- Figure 5-2 Schematic of generic electric grid
- North America
- US electric grid
- Table 5-4 Role of the North American Electric Reliability Corporation (NERC),
- Figure 5-3 Major distribution lines of continental US electric grid
- Electricity generation in Hawaii and Alaska
- Figure 5-4 Major distribution lines of Hawaiian and Alaskan electric grids
- Table 5-5 Role of the North American Electric Reliability Corporation (NERC),
- Table 5-6 Upgrades to US electric grid to handle full CSP production by 2030
- Canadian electric grid
- Figure 5-5 Major distribution lines of Canadian electric grid
- Mexican and Central American electric grid
- Table 5-7 Status of Mexican and Central American electric grids
- Figure 5-6 Major distribution lines within Central America
- Table 5-8 Upgrades to Central American electric grid to handle full CSP production by 2030
- South America
- Table 5-9 Status of South America’s electric grid
- Figure 5-7 Major distribution lines within South America
- Table 5-10 Upgrades to South American electric grid to handle full CSP production by 2030
- Europe and Russia
- Electrical Distribution within Europe
- Table 5-11 Status of European electric grid
- Figure 5-8 Major distribution lines within Europe
- Table 5-12 Upgrades to European electric grid to handle full CSP production by 2030
- Electrical Distribution within Russia
- Table 5-13 Status of Russian electric grid
- Figure 5-9 Major distribution lines within Russia
- Table 5-14 Upgrades to Russian electric grid to handle full CSP production by 2030
- Asia, India, and China
- Electrical Distribution within Asia
- Table 5-15 Status of Asia’s electric grids
- Figure 5-10 Major distribution lines within Asia
- Table 5-16 Upgrades to Asian electric grid to handle full CSP production by 2030
- Electrical Distribution within India
- Table 5-17 Status of India’s electric grids
- Figure 5-11 Major distribution lines within India
- Table 5-18 Upgrades to Indian electric grid to handle full CSP production by 2030
- Electrical Distribution within China
- Table 5-19 Status of China’s electric grids
- Figure 5-12 Major distribution lines within China
- Table 5-20 Upgrades to Chinese electric grid to handle full CSP production by 2030
- Australia
- Electrical Distribution within Australia
- Table 5-21 Status of Australia’s electric grids
- Figure 5-13 Major distribution lines within Australia
- Table 5-22 Upgrades to Australian electric grid to handle full CSP production by 2030
- Africa
- Electrical Distribution within Africa
- Table 5-23 Status of Africa’s electric grids
- Figure 5-14 Major distribution lines within Africa
- Table 5-24 Upgrades to African electric grid to handle full CSP production by 2030
- CSP Market Trends
- Investment Climate
- Figure 5-15 Investments over time and world events
- Public opinion
- Figure 5-16 Public demand for solar energy
- Proliferation of demonstration plants
- Table 5-25 Recent demonstration plants
- Ease of entry compared to other renewable energies
- Table 5-26 New construction costs as a function of location and energy source
- Continued need for premium pricing
- Figure 5-17 Relative declines in power generation by energy type
- CHAPTER 6 COMPETITIVE PROFILES [SELECTED FROM LIST]
- 3M
- Abengoa USA/ Abengoa Spain
- ACCIONA Solar Power/ACCIONA Energia
- Alanod
- Albiasa Solar
- Ausra
- Beacon Solar
- Boeing
- Bright Source Energy
- Carrizo Energy
- Cristaleria Espanola
- Dow chemical
- DuPont
- Ener-T Global
- Epuron
- Eskom
- E-solar
- EuroTrough
- Flabeg
- Florida Power and Light
- Grupo Enhol
- HelioDynamics
- Industrial Solar Technology Corp
- Inland Energy
- Naugatuck Glass
- Paneltec Corp
- Pilkington
- Radco Industries
- ReflecTech
- Samca
- SCHOTT Solar
- Sener Group
- Siemens
- Sinoy Mirror
- Sky Fuel
- SoquiMich
- Solar Millennium AG
- Solar Power Group
- Solel Solar Systems
- Solargenix Energy
- Sopogy
- Stirling Energy Systems
- CHAPTER 7 END USERS
- Public End Users
- Utility Companies
- Table 7-1 US Utilities operating CSP
- Public perception of renewable energy
- Figure 7-1 Changes in public perception over time
- Perception of CSP vs. other renewable energy sources
- Trends in public perception
- Public willingness to pay premium pricing for renewable energy
- Figure 7-2 Distribution of premium price options and acceptance
- Industrial End Users
- Uses by industry
- Table 7-2 CSP Industrial Applications
- Motivation factors for industrial users
- Table 7-3 Leading motivators for industrial CSP use
- Implementation Trends of industrial users
- Table 7-4 Implementation Trends of Industrial CSP Applications
- Appendices
- List of Abbreviations
- Selected marketers contact information
- Selected Organizations, Research Institutes, and Universities- contact information
- Installed and Planned CSP Facilities
- Selected CSP Facilities: Profiles and contact information